VANTAGETM

System Overview

Mode:
🔴

Vantage Point

Critical Action Required

You have 1 project at risk of rejection due to binding constraints. The Valley-North 345kV corridor is the bottleneck for 3 projects.

Current Cycle Status

System Status Summary

8 projects screened this cycle. 4 are feasible, 3 require conditional planning, 1 face blockers.

5 constraints identified as binding across the portfolio. The Valley-North 345kV corridor dominates feasibility outcomes for 3 projects.

4 required upgrades span transmission, substation, and control systems. Total portfolio upgrade investment exceeds $170M with dependencies across multiple projects.

Key Metrics

8
Projects Screened
4
Feasible
3
Conditional
1
Infeasible
5
Constraints
4
Upgrades

System Binding Constraints

Constraint IDTypeContingency TriggerBase SeverityBinding LikelihoodStatus
L-123_SUB1ThermalN-1 VN-Line192%
87%
Action Required
V-456_CST2VoltageN-2 Line1+Gen378%
65%
Monitored
S-789_EZ04StabilityN-1 Cap165%
52%
Monitored
T-234_NSB5ThermalN-1 Transformer188%
73%
Action Required
V-567_RSM3StabilityN-1 MainLine45%
28%
Monitored

Items Requiring Attention

PRJ-004: Gas-Fired Generation Delta

Escalation required — Feasibility constraint cannot be mitigated within acceptable cost-benefit threshold.

PRJ-003: Battery Storage Gamma

Conditional feasibility — Awaiting North Substation transformer upgrade schedule confirmation.